Given an actual outcome of $26,000 and a flexible budget value of $13,000, what is the flexible budget amount?
Multiple choice question for Flexible Budget and Management Control. Select an option, then review the explanation below.
Explanation
The flexible budget amount remains $13,000 as stated, regardless of the actual result of $26,000.
More Flexible Budget and Management Control MCQs
Practice related questions from the same subject.
- 1.Given that the sales budget variance for operating income is $58,000 and the static budget figure is $15,000, what is the value of the flexible budget?
- 2.Given a flexible budget value of $82,000 and an actual outcome of $45,000, what is the variance between the flexible budget and the actual result?
- 3.Given a flexible budget of $27,000 and a flexible budget variance of $12,000, what is the actual amount recorded?
- 4.Given a sales budget variance of $47,000 and a flexible budget figure of $77,000, what is the value of the static budget?
- 5.Given a sales budget variance of $57,000 and a flexible budget total of $97,000, what is the value of the static budget?