What term describes the difference between the flexible budget figure and the actual outcome?
Multiple choice question for Flexible Budget and Management Control. Select an option, then review the explanation below.
Explanation
The flexible budget variance refers to the discrepancy between the flexible budget amount and the actual results. Other options do not correctly define this difference.
More Flexible Budget and Management Control MCQs
Practice related questions from the same subject.
- 1.Given that the sales budget variance for operating income is $58,000 and the static budget figure is $15,000, what is the value of the flexible budget?
- 2.Given a flexible budget value of $82,000 and an actual outcome of $45,000, what is the variance between the flexible budget and the actual result?
- 3.Given a flexible budget of $27,000 and a flexible budget variance of $12,000, what is the actual amount recorded?
- 4.Given a sales budget variance of $47,000 and a flexible budget figure of $77,000, what is the value of the static budget?
- 5.Given a sales budget variance of $57,000 and a flexible budget total of $97,000, what is the value of the static budget?