What is the primary function of a retarder in concrete?

Building Materials and Construction MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Building Materials and Constructioncivil-engineering-mcqs › building-materials-and-construction
Published
9 Jan 2019
Last updated
28 May 2026

Browse all Building Materials and Construction MCQs

Choose the correct answer

Explanation

Option A is correct because a retarder is used to delay the initial setting time of cement paste in concrete, allowing for extended workability. Option B is incorrect as retarders do not speed up setting. Option C refers to waterproofing, which is unrelated to retarders. Option D relates to workability, but retarders primarily affect setting time rather than mix consistency.