Given an activity with optimistic, pessimistic, and most likely durations of 5 days, 17 days, and 8 days respectively, what is the expected completion time?

Construction Planning and Management MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Construction Planning and Managementcivil-engineering-mcqs › construction-planning-and-management
Published
19 Jan 2019
Last updated
28 May 2026

Browse all Construction Planning and Management MCQs

Choose the correct answer

Explanation

The expected time (TE) is calculated using the formula: (Optimistic + 4 × Most Likely + Pessimistic) / 6. Substituting the values: (5 + 4×8 + 17) / 6 = (5 + 32 + 17) / 6 = 54 / 6 = 9 days.