During the construction of super-elevated curves on highways, in which direction should the rolling process be carried out?

Highway Engineering MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Highway Engineeringcivil-engineering-mcqs › highway-engineering
Published
12 Jan 2019
Last updated
28 May 2026

Browse all Highway Engineering MCQs

Choose the correct answer

Explanation

In building super-elevated highway curves, rolling is performed from the lower edge towards the upper edge to ensure proper compaction and stability of the pavement.