If the direct material expenses amount to $75,000 and the direct manufacturing labor costs are $20,000, what is the total prime cost?
Explanation
Prime cost is the sum of direct material cost and direct manufacturing labor cost. Here, $75,000 (materials) + $20,000 (labor) equals $95,000, which is the prime cost.