If the prime cost amounts to $50,000 and the direct labor cost is $10,000, what is the value of the direct material cost?

Choose the correct answer

Explanation

The prime cost is the sum of direct material cost and direct labor cost. Given the prime cost is $50,000 and direct labor is $10,000, the direct material cost equals $50,000 minus $10,000, which is $40,000.