In the process of constructing water bound macadam roads, what is the proper order of steps following the distribution of coarse aggregates?

Highway Engineering MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Highway Engineeringcivil-engineering-mcqs › highway-engineering
Published
12 Jan 2019
Last updated
28 May 2026

Browse all Highway Engineering MCQs

Choose the correct answer

Explanation

The correct sequence after laying coarse aggregates involves first dry rolling to stabilize the material, then applying screening to fill voids, followed by wet rolling to compact the layers, and finally adding filler to bind the aggregates together effectively.